Both trades are close friends so I’m sure they will do everything to help resolve it.
builder: laid ply, mats, pro warm
floorer: screed to cover and protect system. Back 2 weeks later for 2nd screed layer across whole living space. Flooring down a week later.
System would of been on...
Not a cheap job. Our builders who opened up a large living space laid the pro warm in kitchen and dining room. The problem areas seem to be where the underfloor section meets the living room which does not have pro warm.
They used 6 and 12mm plys and screeded the whole space to get a level...
Hello,
If anyone can have a look at the attached. Warm up sticky mats have been used with warmup insulation boards. Floor levelling screed and then Karndean flooring.
You can see a raised section in the floor coming through and has been slowly getting worse over the past few weeks.
...