hi, the form is in my possession mate, don't have it online?
20kva? im confused now, did you not say 70kva would be minimum for a 3phase installation??
sorry for cinfusion
compressor is a 4hp 400v and works upto 10 bar or 150psi
DOL start?? whats that?
as far as I know its 8 x 6ft fluorescents
no automated test lane
starts per hour for air could be upto 5
and ramps would be similar id think?
I do have a package from ramp company coming so can get full specs...
Hi as title I have a form from SP Energy networks, they are asking for a rough load (kva) of the connections I require in my garage
basically we are building an MOT station and a storage unit, both units will have 3phase brought into them.
the mot station will have 2 x ramps and an air...