Is the use of SY cable allowed on construction sites
4 off 3P 10kva site transformers which may get moved around from time to time
(all located inside) fed from MDA using SY Cable because more flexible than SWA
Will be using internal CPC but not sure steel braid is suitable to meet regs,even...