Thanks guys,
@binkyWith Scottish Power, I don't want to invalidate my system, hence the reason for inquiring bud.
@MHarv do i need to swap out my inverter, as i would want to keep as is, and install batteries as an addon if you know what i mean.
Will check out ITS Technologies bud
what would be the battery output for the system I have.
Thanks again guys
I am with SP Energy , MSC certified G98 <3.68kWh Solax X1 Boost 3.68kWh inverter with split PV Array East/West 2.56kWh each total 5.2kWh Array seperste Mini CU split tails from Henley block with iBoost+install plus Hypervolt 2.0 EV Charger again on seperate Mini Single 40A with split tails from Henley block (Henley block prior was just 2 split tails to Main Consumer Unit now totals 6 split tails after Solar Pv and EV Charger.
Solax HV (High Voltage) Battery System consisting of 1 Main Master LFP Battery 5.8kWH and 1 Solax Slave 5.8kWh total capacity 11.6kWh but Only 10.4kWh Useable due to DOD (Depth of Discharge)
90% by Solax.
SP Energy do G99 Fast Track for adding Battery Storage with G98 and G99 Type Tested ENA Registered Approved Inverters
within 2 weeks, my application which I did
Includes providing details of Existing Generation Installs plus the New additional
Generation or Battery Storage which in my case Solax X1 AC-3.6kWh G98 & G99 Type Tested ENA Registered Approved inverter and Battery Capacity; DNO more interested in the Inverter, all done prior to purchasing as stated by the G99 EREC document to get Approval Confirmation to go ahead with Install.
SP Energy did say Hybrid Inverter was possible with Batteries, but DeCommissiong Form would have to made for Solax X1 Boost 3.6kWh inverter (plus Qualified Electrician cost) to update their records, legal obligation under ENREC G98 document for home owner and start New Application for Hybrid requiring MSC Certified install again and new application for SEG plus inform Electric Energy Provider
Of the Changes as well to be totally Legal.
Easy and quickest route was apply for G99 Fast Track approval first with DNO, purchase Battery AC System (48volt LV or >100volt Battery Configuration)
That’s another topic to consider for discussion.
Battery installation does not need MSC certificate, a CPS qualified Electrician is legally required to fulfil the connection and Commissioning for the relevant Forms to be filled as required by the DNO.
I fitted the Battery System together, fitted Inverter to wall all cables 6mm2 to AC Isolator left rest for Electrician to Connect to Mini CU and Commission system and fill in the parts of forms printed out he is required for DNO.
IMHO I would Keep your setup inverter and install AC system unless you go through all the bureaucracy of Decommissioning, Re-Applying with DNO and SEG for Export EXPAN number with Energy provider again
which requires DNO Approval letter or email and new MSC Certificate (Has your Inverter type on it)
Very long winded but has to be done to keep DNO records correct, upto date as well as the records for your Energy Provider.
Your Installer can do all this but is reflected in price you pay, you need to discuss with installer what he is happy with and go from there, some installers will only do the install fully again reflected in the price, mine was happy to do what I could but not Connection, even the wiring for AC inverter and AC Isolator were left undone so he could verify the wiring and torque check before attaching AC cable to inverter and putting on AC Isolator Cover back on and securing.
But you can save some expense in the process. Hope this helps