ruston
Well-known member
I'm impressed with your engineering skills and equipment too.
According to me you would need a 300mm one????
What size cable do you have running the 300 metres now?? According to me you would need a 300mm one???? I cannot even find 300mm 2 core, but the 3 core would be about £20,000 and the cable would weigh about 4 tons....
The three phase 4 core one though [for 60a], would only be 70mm, would cost about £5000 and would weigh about 1 1/4 tons.. Would be just under 1 1/2" diameter compared to over 2" for the single phase 100a one AND, you would still have nearly three times the power.....
It is a no brainer..
john..
Where do you get that from? You seem to be getting around double what I would say would be needed.
Where do you get that from? You seem to be getting around double what I would say would be needed.
Am i missing something??
My family member that just had their 100A SP supply in to the new house had a 185mm 4 core cable put it by the DNO the length of run was 298m helpfully! All buried.
If you ask for a three phase supply, you will find it is only very slightly more than a single phase one. It makes no difference to the DNO at all, BUT and it is a VERY big but, they would MUCH rather give you a three phase 60A supply than a 100A single phase one, because they have to spread the load as equally as they can over all three phases for reasons i will not bore you with!!
sorry I miss read this... I get it now... I think. They won't be very keen on taking 2x100A supplies off one of their phases. Even though the SP transformer is already fitted they might be more interested in replacing with a TP transformer as it would be balanced across then.