Working with a mate on one of his jobs,,,,,40 downlighters in 5 rooms

customer insisted on buying them,,,,job started friday with the promise of the downlighters being avaiable Monday.

guess what,, he hasn't ordered the lights yet so we can't do any more att

at what stage would you start charging 'standing time' and at what rate ?

we have given him Monday as a freebie only because a one day job popped up but we wont be starting again until Wednesday

 

SPECIAL LOCATION

Trailer Boy - Electrician.
Joined
Mar 28, 2008
Messages
13,633
Reaction score
317
Working with a mate on one of his jobs,,,,,40 downlighters in 5 roomscustomer insisted on buying them,,,,job started friday with the promise of the downlighters being avaiable Monday.

guess what,, he hasn't ordered the lights yet so we can't do any more att

at what stage would you start charging 'standing time' and at what rate ?

we have given him Monday as a freebie only because a one day job popped up but we wont be starting again until Wednesday
To be perfectly honest...

I don't think I would have started the job until confirmation that the materials are actually physically there! :| :(

I don't like even confirming I can definitely start my own jobs unless I know I can see touch and smell the goods to be installed...

I hate been delayed cuz one farty cog is out of synch with the daily routines... X(

especially when I know I could be doing other work...

either paid proper stuff or even just sorting out my own stuff at home...

Not good hanging around! :( :(

 

Theorysparky

Domestic Electrician
Joined
Feb 18, 2008
Messages
4,233
Reaction score
0
lesson learnt i think

and i just know that the downlighters will be wrong for the job when they arriveX(

 

M107

Billy-the-Kid
Joined
Feb 18, 2008
Messages
5,562
Reaction score
28
Location
Berkshire
I do hate it when customers say they'll buy the materials, it normally ends up being cheap B&Q or IKEA tat.

 

kme

Fridge Keyholder™
Joined
Mar 7, 2008
Messages
9,987
Reaction score
0
Location
In the office again.
Agreed M107. If they want to get their own materials, I generally send `em to my preferred suppliers. Then I`ll call `em a couple of days beforehand, to confirm they`ve actually got the stuff.

Not much help to you really, Theo; but if I did have this situation, I`d HAVE to charge almost immediately.

 

norv

Senior Member
Joined
Feb 16, 2008
Messages
126
Reaction score
0
Same here. When fitting downlights I like to use those Click connectors & get the downlights connected to the transformers before I get to the job. Do ur IR tests, then just plug the things in.

All depends on the customer if you charge extra time.

 

Theorysparky

Domestic Electrician
Joined
Feb 18, 2008
Messages
4,233
Reaction score
0
i did suggest we charged the customer straight away but we think there could be a lot more work that needs doing in the property.....

lights in garage dont work....wine cellar lighting faulty all sockets switches need replacing and it goes on.....

dont think we should rock the boat just yet ;)

 
Joined
Feb 27, 2008
Messages
11,030
Reaction score
0
This is the problem when customers get materials. I had this on a job, the downlighters they got from wickes and they were not fire rated. Luckily one of my wholesalers delivered some out the same day so there was no hold up. Some of these customers do your head in. I told them they would need an extractor in the extension as it was now part of the kitchen they said no because it wasn't on the plans. Any way I have now got to go back to install fan so job can be signed off, great when its all been plastered. Its going to cost them a lot more than if i had done it at first fix.

batty

 

ElectekAir

Well-known member
Joined
Jul 3, 2008
Messages
449
Reaction score
0
I dont let customers but the materials for this exact reason......

You cant charge a wating fee or down time unless it is on your qoutation or company terms and cond.. and then is signed by the customer ( you would not win if it went to court) i've had this prob and now have signed qoutations

Just make a note and add the lost cost into any future work :)

Craig

 

SPECIAL LOCATION

Trailer Boy - Electrician.
Joined
Mar 28, 2008
Messages
13,633
Reaction score
317
I dont let customers but the materials for this exact reason......You cant charge a wating fee or down time unless it is on your qoutation or company terms and cond.. and then is signed by the customer ( you would not win if it went to court) i've had this prob and now have signed qoutations

Just make a note and add the lost cost into any future work :)

Craig
Couldn't agree more...

My normal procedure is to provide a quote with a duplicate copy for the customer to sign..

I have a space for them to write their preferred start date for the work as well.

I dont order materials until I have a signed quote back in my grubby mits..

saves loads of agro! :D

 

extension15

Distinguished Member
Joined
Feb 13, 2008
Messages
1,658
Reaction score
0
> Relying on customers to buy the materials<

I would say is sometimes (often?) this a bad move, I try and tell the customers that want to go up this route, what to buy..

(Clients don't tend to consider all practical issues, with the product(s))

:D

 

baldelectrician

Well-known member
Joined
Mar 22, 2008
Messages
180
Reaction score
0
Unless it is fancy lights or fancy palte swithces I prefer to buy.

It the client wants a certain style they get directed to my local wholesaler and they pick what they like and get my discount- the wholesaler is good enough to steer the client away from tat.

I perfer not to do jobs where the client supplies the stuff- if I do it is on a time and materials basis. Then if they buy fiddly lights then it is more time and more money.

Most people listen to advice when you point out it will be cheaper

 

Admin1

Forum Founder
Joined
Feb 6, 2008
Messages
10,229
Reaction score
-1
Having said all that, if you`re approaching vat threshold, and don`t want to be vat reg`d; you might HAVE to let them buy the materials; just to keep your turnover down a bit!
Yes Mate. Agreed.

 