The story is:
Whole 8 roomed house is wired in lead sheathed cables & has the old cu set up that I posted pictures of in the picture section. No equipotential bonding, no supplimentary bonding......Apart from (and Im suprised the dno fitted it) the brand spanking new service head & tails its basicaly a 1900 & plonk install, if you know what I mean.
What the customer wants is a new set of tails from Henleys supplying & new cu & the lounge/diner sso circuit rewired & equi bonds only for now (lounge/diner lighting will be done when they start upstairs work).
I gave them a quote to do the whole house in one hit & came in at 4.5K, but they are wanting it done in stages as they renovate each room over a 6 month period.
So I re-quoted for the cu, equi bonds & ring at
Whole 8 roomed house is wired in lead sheathed cables & has the old cu set up that I posted pictures of in the picture section. No equipotential bonding, no supplimentary bonding......Apart from (and Im suprised the dno fitted it) the brand spanking new service head & tails its basicaly a 1900 & plonk install, if you know what I mean.
What the customer wants is a new set of tails from Henleys supplying & new cu & the lounge/diner sso circuit rewired & equi bonds only for now (lounge/diner lighting will be done when they start upstairs work).
I gave them a quote to do the whole house in one hit & came in at 4.5K, but they are wanting it done in stages as they renovate each room over a 6 month period.
So I re-quoted for the cu, equi bonds & ring at