Just had a schematic from a firm I'm doing a PV install for tomorrow,
I'm puzzled as to the order he wants the AC connected,
He has split tails at ISCOs/Henleys, into generation meter, into mini CU, into AC isolator,
The way I've always done it in past is,
mini CU, Generation meter, AC isolator,
Is his way of doing it acceptable,?
Or do I need to pull him on it,?
tbh, I'm not very comfortable with his arrangement