- Joined
- Dec 25, 2011
- Messages
- 5,468
- Reaction score
- 78
No doubt a typical newbie question. Long story. I've been in touch with EDF about getting an REC switch / isolator fitted to my property. This has taken since last Wed with calls to them Weds, Thurs, Fri and today. Getting to the end of it hopefully with finally a really helpful girl who has phoned me back as promised when she said she would. She said that they will disconnect in the morning and reconnect pm after an electrician has fitted the switch. She did say that prior to reconnecting they will want to see an "icert". I said "What does that mean by an icert then?". I was pretty sure of what she meant but honestly had not heard it called this. She basically said "I don't know what it stands for, it's a special certificate........called an icert!" I countered with "So do you mean a Minor Electrical Installation Works Certificate or an Electrical Installation Certificate?". She DIDN'T know and give here her due went off to ask her manager then called me back. I also said could she check if it would be OK for me to fit, I said I hold the 17th and 2330 Level 3.
She came back and it is the full Electrical Installation Certificate they want. As for the appointment she was quoting 10 to 14 days. I said (already told them this last week) that the stand alone RCD protecting the whole board is suspect - its a TT system by the way. "What's an RCD?" she said. I explained as simply as I could and she said she would call her meter team and call me back. This she did and as it is NOT an emergency they are coming on Monday 23rd January.
What I can't quite figure is in this case why a full Electrical Installation Certificate is needed rather than a Minor Electrical Installation Works Certificate . I guess its that they won't re-energise an unsafe system? Shoot me down please if I'm missing something. The reason I want the REC fitted is so that I can safely isolate the old suspect system and get on with sorting it, the install out properly. Fit a new CU and then use it as my first ELECSA job. It seems a bit "chicken and egg" in that I can't do the live tests until the power is back on i.e earth loop and RCD tests. If I can't do the live tests then I can't complete the Schedule Of Tests properly?
Any suggestions? Thanks
She came back and it is the full Electrical Installation Certificate they want. As for the appointment she was quoting 10 to 14 days. I said (already told them this last week) that the stand alone RCD protecting the whole board is suspect - its a TT system by the way. "What's an RCD?" she said. I explained as simply as I could and she said she would call her meter team and call me back. This she did and as it is NOT an emergency they are coming on Monday 23rd January.
What I can't quite figure is in this case why a full Electrical Installation Certificate is needed rather than a Minor Electrical Installation Works Certificate . I guess its that they won't re-energise an unsafe system? Shoot me down please if I'm missing something. The reason I want the REC fitted is so that I can safely isolate the old suspect system and get on with sorting it, the install out properly. Fit a new CU and then use it as my first ELECSA job. It seems a bit "chicken and egg" in that I can't do the live tests until the power is back on i.e earth loop and RCD tests. If I can't do the live tests then I can't complete the Schedule Of Tests properly?
Any suggestions? Thanks