- Joined
- Feb 11, 2022
- Messages
- 14
- Reaction score
- 1
Hi all.
I'm new here and I'm not an electrician - I was hoping to get a little bit of advice on a solar installation that I'm looking into.
First off, I won't be doing this installation (I will get an electrician to do it), but I would like to be involved in the design of the system and to at least understand it so that I can make informed decisions around some elements, so I'd really welcome any guidance. I do have a background in electronics so have a rough idea of the physics etc involved and know enough to leave the dangerous stuff to an expert.
I have a slightly complex domestic mains setup. We have an old 18c house which we recently refurbished. When we did, we went all electric (we're in a remote location and I'm not a fan of on premise oil). The heating is underfloor electric element and as a result of having it the electricity board required us to upgrade our supply.
So we have 3 phase coming in, out of which we are using 2 of the 3 phases. One consumer unit (phase 1) feeds the underfloor heating and 9kw hot water boiler (which in turn heats a couple of cylinders) and the other consumer unit (phase 2) powers the rest.
Ground floor heating when all switched on is about 18.5kw and upstairs is about 12kw. For the rest of the house I've never seen us go over 10kw, and typically we peak at about 8kw, depending on if the dryer/washing machine etc are running. We're all LED lighting and actually don't use much, other than the floor which is thirsty...
What I'd like to get out of a solar PV design is to get the floor and hot water as much as possible off-grid. I have no need or desire to sell electricity back to the grid and instead would like to use as much of what we generate as I can. I appreciate I need to be grid tied - or at least I think I do - in order to have the grid as my backup for when there's no sun but I'm assuming the value of that will be peanuts and I'd rather try and use what I generate than sell it.
It was always the plan to do this when we bought the place - the cost of electricity increasing significantly in a couple of months has made us want to get on with it now.
In basic logic, I am thinking of something like this:-
In winter
1. In the morning, pump all available solar PV energy into the downstairs floor.
2. Any excess, pump it into the hot water cylinders (they have immersion heating elements currently unused)
3. Any excess beyond that pump into batteries for later use
4. Any excess beyond that use for the domestic circuit
5. In the afternoon, use to offset the domestic supply (possible manual override if it's really cold and we need more heating)
Any shortage, pull in either from battery if available or grid if not.
Space wise I have, subject to planning, some ground where I can put between 24kw and 30kw of panels. The plot of ground is about 125m from the house so I am conscious of cable losses - my thinking at the moment is to set up the strings to run at about 450v DC to reduce the loss as much as possible on 10AWG cables for the long run. I'm therefore looking at inverters with an up to 500v or so max DC input (fortunately there seem lots like this to choose from). I have just started to understand and explore micro-inverters as an option, but I like the idea of high voltage DC at the moment. The ground area is totally unshaded and it's my land so I can keep it that way (this is all subject to planning permission of course, but I have high hopes and have seen similar projects granted in our region).
So, the bit I can't quite get my head around is how I switch across the two phases to try and achieve what I want - which is the ability to push all power into one consumer unit when needed but switch it out to both when not.
I've created a diagram to help explain what I want to try and achieve based on what I think I need, which is a pair of inverters that are capable of parallel operation. It's basically 2 modes - "Split" which is just one inverter feeding each of my 2 consumer units/phases and "Winter" mode which is both inverters feeding phase 2/consumer unit 2. In both cases, excess energy going into hot water and/or battery.
I would be grateful for any tire kicking/thoughts on this or even if what I'm looking to do isn't possible. Incidentally I am aware that I won't get the theoretical maximum kW out of this and in winter it could be quite low. Heating is my largest cost, so the idea is whatever energy is available in Winter, put it in the floor. Downstairs the under floor elements are encased in concrete and once heated up continue to radiate heat for quite a few hours.
Many thanks!

I'm new here and I'm not an electrician - I was hoping to get a little bit of advice on a solar installation that I'm looking into.
First off, I won't be doing this installation (I will get an electrician to do it), but I would like to be involved in the design of the system and to at least understand it so that I can make informed decisions around some elements, so I'd really welcome any guidance. I do have a background in electronics so have a rough idea of the physics etc involved and know enough to leave the dangerous stuff to an expert.
I have a slightly complex domestic mains setup. We have an old 18c house which we recently refurbished. When we did, we went all electric (we're in a remote location and I'm not a fan of on premise oil). The heating is underfloor electric element and as a result of having it the electricity board required us to upgrade our supply.
So we have 3 phase coming in, out of which we are using 2 of the 3 phases. One consumer unit (phase 1) feeds the underfloor heating and 9kw hot water boiler (which in turn heats a couple of cylinders) and the other consumer unit (phase 2) powers the rest.
Ground floor heating when all switched on is about 18.5kw and upstairs is about 12kw. For the rest of the house I've never seen us go over 10kw, and typically we peak at about 8kw, depending on if the dryer/washing machine etc are running. We're all LED lighting and actually don't use much, other than the floor which is thirsty...
What I'd like to get out of a solar PV design is to get the floor and hot water as much as possible off-grid. I have no need or desire to sell electricity back to the grid and instead would like to use as much of what we generate as I can. I appreciate I need to be grid tied - or at least I think I do - in order to have the grid as my backup for when there's no sun but I'm assuming the value of that will be peanuts and I'd rather try and use what I generate than sell it.
It was always the plan to do this when we bought the place - the cost of electricity increasing significantly in a couple of months has made us want to get on with it now.
In basic logic, I am thinking of something like this:-
In winter
1. In the morning, pump all available solar PV energy into the downstairs floor.
2. Any excess, pump it into the hot water cylinders (they have immersion heating elements currently unused)
3. Any excess beyond that pump into batteries for later use
4. Any excess beyond that use for the domestic circuit
5. In the afternoon, use to offset the domestic supply (possible manual override if it's really cold and we need more heating)
Any shortage, pull in either from battery if available or grid if not.
Space wise I have, subject to planning, some ground where I can put between 24kw and 30kw of panels. The plot of ground is about 125m from the house so I am conscious of cable losses - my thinking at the moment is to set up the strings to run at about 450v DC to reduce the loss as much as possible on 10AWG cables for the long run. I'm therefore looking at inverters with an up to 500v or so max DC input (fortunately there seem lots like this to choose from). I have just started to understand and explore micro-inverters as an option, but I like the idea of high voltage DC at the moment. The ground area is totally unshaded and it's my land so I can keep it that way (this is all subject to planning permission of course, but I have high hopes and have seen similar projects granted in our region).
So, the bit I can't quite get my head around is how I switch across the two phases to try and achieve what I want - which is the ability to push all power into one consumer unit when needed but switch it out to both when not.
I've created a diagram to help explain what I want to try and achieve based on what I think I need, which is a pair of inverters that are capable of parallel operation. It's basically 2 modes - "Split" which is just one inverter feeding each of my 2 consumer units/phases and "Winter" mode which is both inverters feeding phase 2/consumer unit 2. In both cases, excess energy going into hot water and/or battery.
I would be grateful for any tire kicking/thoughts on this or even if what I'm looking to do isn't possible. Incidentally I am aware that I won't get the theoretical maximum kW out of this and in winter it could be quite low. Heating is my largest cost, so the idea is whatever energy is available in Winter, put it in the floor. Downstairs the under floor elements are encased in concrete and once heated up continue to radiate heat for quite a few hours.
Many thanks!

Last edited: