VIresistance
New member
Hi
I was wondering if someone help me with this please. I have my 2394/95 recently.
I was testing a industrial DB today and phase rotation at main switch was anti clock wise which is wrong.
The board is sub main from main board and plant room.
Why is wrong and is there any other reason it could course it to be wrong sequence part of wrong connection?
I am testing a few new circuits on that board and I will sign a certificate for it.
What do I need to do about it?
Thank you