Hello everyone I'm new here, I'm just after a bit of advice and guidance if that's ok, hopefully posted in correct place.
I have currently taken on 2 commercial units to manage and rent out, there is currently incoming supply on the ground floor with a fuse board which will be running a car spraying garage and a further fuse board upstairs which controls office sockets, lights, boiler for what will be approximately 5 offices once refurbished. There is 1 meter which is on the ground floor by the incoming supply.
I'm looking to have a sub meter installed , however at present I have had 3 electrical contractors in and all told me different things which has left me with a headache as what to do.
If someone could be of some assistance in giving me advice I would appreciate it.
I have been told i need the following.
1. Incoming tails need to be removed g/f fuse board and put in a connector block (unsure of term they used)
2. From this connector block new tails will be installed to a switch fuse, and then from there to gf fuse board.
3. Also from connector block would be 25mm steel wire armour cable approx 45 metres up to 1st floor into a switch fuse, then from there would be meter tails to sub meter and sub meter to 1st floor fuse board.
4. What would happen to existing cable that goes to main switch on 1st floor fuse board? Surely this cable can be used?
Second company told me.
They would install as follows.
1. Disconnect tails to gf fuse board and use a connection block
2. Install 2 x switch fuses by gf fuse board
3. Run tails from switch fuse to gf fuse board
4. Connect steel wire armour cable from switch fuse to sub meter still on gf and then from sub meter run steel wire armour to 1st floor consumer unit.
5. Again what would happen to existing supply cable to 1st floor fuseboard
This way would make both main meter and sub meter be in same location.
The fuse board on the 1st floor I'm told has 16 fuses in use supplying power to many sockets, lights, communal toilets, communal kitchen, communal corridors , heating boiler etc etc
Both seem completely different approaches and both are coming in at approximately 1 thousand pound to install.
I'm confused and don't want to be ripped off and I'm hoping there is some individual on here that can point me in the right direction . This work is in Gloucestershire and the companies who have quoted are well known big companies but I'm confused as to who's doing what and if correct.
I have spoken to a self employed electrician from Cheltenham who is hoping to come take a look for me next week, however I don't want to confuse matters more as my heads pounding from information which changes every time I get someone to come and look.
I look forward to anyone's help, just looking for some pointers on who's basically doing the best way and if a rough estimate of £1000 sounds expensive as it does to me and being female I'm trying to make sure I'm not taken advantage of.
I have currently taken on 2 commercial units to manage and rent out, there is currently incoming supply on the ground floor with a fuse board which will be running a car spraying garage and a further fuse board upstairs which controls office sockets, lights, boiler for what will be approximately 5 offices once refurbished. There is 1 meter which is on the ground floor by the incoming supply.
I'm looking to have a sub meter installed , however at present I have had 3 electrical contractors in and all told me different things which has left me with a headache as what to do.
If someone could be of some assistance in giving me advice I would appreciate it.
I have been told i need the following.
1. Incoming tails need to be removed g/f fuse board and put in a connector block (unsure of term they used)
2. From this connector block new tails will be installed to a switch fuse, and then from there to gf fuse board.
3. Also from connector block would be 25mm steel wire armour cable approx 45 metres up to 1st floor into a switch fuse, then from there would be meter tails to sub meter and sub meter to 1st floor fuse board.
4. What would happen to existing cable that goes to main switch on 1st floor fuse board? Surely this cable can be used?
Second company told me.
They would install as follows.
1. Disconnect tails to gf fuse board and use a connection block
2. Install 2 x switch fuses by gf fuse board
3. Run tails from switch fuse to gf fuse board
4. Connect steel wire armour cable from switch fuse to sub meter still on gf and then from sub meter run steel wire armour to 1st floor consumer unit.
5. Again what would happen to existing supply cable to 1st floor fuseboard
This way would make both main meter and sub meter be in same location.
The fuse board on the 1st floor I'm told has 16 fuses in use supplying power to many sockets, lights, communal toilets, communal kitchen, communal corridors , heating boiler etc etc
Both seem completely different approaches and both are coming in at approximately 1 thousand pound to install.
I'm confused and don't want to be ripped off and I'm hoping there is some individual on here that can point me in the right direction . This work is in Gloucestershire and the companies who have quoted are well known big companies but I'm confused as to who's doing what and if correct.
I have spoken to a self employed electrician from Cheltenham who is hoping to come take a look for me next week, however I don't want to confuse matters more as my heads pounding from information which changes every time I get someone to come and look.
I look forward to anyone's help, just looking for some pointers on who's basically doing the best way and if a rough estimate of £1000 sounds expensive as it does to me and being female I'm trying to make sure I'm not taken advantage of.