Hello,
I'm soon to have a SolaX X1-Fit G4 5kW inverter + 11.6kW TP58 battery installed.
https://midsummerwholesale.co.uk/buy/solax/solax-x1-g4-fit-5-tp58
I already have an Aurora Power-One 3.6kW inverter which is managing my solar panels.
I've been trying to break down the manual to see what would be the best install for me and I've been advised by the seller and SolaX that to get the 2 inverters to talk, I would need either 2 CT clips or 2 CHINT meters.
I've decided to go the option of 2x CHINT meters as I'm unable to get another CT clamp from the seller.
There is nowhere on the manual or the internet on how to wire up 2 CHINT meters to an RJ45 connector.
Does anyone have any experience with this, especially if you have a SolaX install?
I'm also having a pre-pay meter installed for my tenants.
Speaking to my electrician, he has not installed a meter where a solar setup was done.
Please could someone advise if the solar/battery power would affect an install of a pre-pay electric meter?
Also, would all energy (from battery or solar) pass through the pre-pay meter be metered as used energy or does it pass through somehow as free energy?
Sorry for the silly questions.
Thank you!!!
I'm soon to have a SolaX X1-Fit G4 5kW inverter + 11.6kW TP58 battery installed.
https://midsummerwholesale.co.uk/buy/solax/solax-x1-g4-fit-5-tp58
I already have an Aurora Power-One 3.6kW inverter which is managing my solar panels.
I've been trying to break down the manual to see what would be the best install for me and I've been advised by the seller and SolaX that to get the 2 inverters to talk, I would need either 2 CT clips or 2 CHINT meters.
I've decided to go the option of 2x CHINT meters as I'm unable to get another CT clamp from the seller.
There is nowhere on the manual or the internet on how to wire up 2 CHINT meters to an RJ45 connector.
Does anyone have any experience with this, especially if you have a SolaX install?
I'm also having a pre-pay meter installed for my tenants.
Speaking to my electrician, he has not installed a meter where a solar setup was done.
Please could someone advise if the solar/battery power would affect an install of a pre-pay electric meter?
Also, would all energy (from battery or solar) pass through the pre-pay meter be metered as used energy or does it pass through somehow as free energy?
Sorry for the silly questions.
Thank you!!!