Hi there,
Could someone clarify something for me, please...
Getting a quote from a fairly big company in the NE for solar PV and a battery solution. Size of array is 4.86kW.
Northern power grid, our DNO, says anything over 3.86kWh needs it however the solar company say you only need a G99 application if we include optimisers on the panels.
I would have thought whether optimisers are included or not is irrelevant. Surely it's the size of the array?
Any help appreciated.
Thanks!