Client wants a supply to detached garage (lighting and a few sockets for freezer etc nothing heavy) 6 metres from house. Also supply to summer house 6 meters from garage (12m from house) again basic lighting and couple of sockets. TNS and nothing extraneous in either structure.
So SWA from non-rcd way in house CU.
Do I need a small CU (RCD protected) in each building (supplying second CU from live side of main switch from first CU) or should I just run SWA to summer house from a RCD protected MCB in the garage?
So SWA from non-rcd way in house CU.
Do I need a small CU (RCD protected) in each building (supplying second CU from live side of main switch from first CU) or should I just run SWA to summer house from a RCD protected MCB in the garage?