opentoideas
Member
- Joined
- Mar 3, 2016
- Messages
- 13
- Reaction score
- 0
My current project is so far outside the norm I am hoping that the more experienced here can have a look and see if what I want to do is acceptable as I am having a hard time applying the regs to the different aspects when combined as a whole.
While this is my own property not a customer I obviously want to do it within the regs and my head is spinning and I don’t want to miss anything as selective optimism is easy to indulge when you are looking to make it work.
To set the scene – I have a couple of workshops fed from a domestic single phase supply.
I also have a 50KVA 3-phase generator supplying machinery within the workshops as required.
At present the 2 systems are separate
Up to this point all is well, however, I had the “sensible “ idea that while the generator is running I might as well supply the workshops single phase requirements…………
I have a 3 phase transfer panel and while I know I can achieve the desired outcome it is so unorthodox that I would appreciate a sanity check.
First off the changeover is delayed and has mechanical interlocks so mains and generated supplies remain isolated from each other in all circumstances.
The plan would be to have the single phase supply come in to a split load CU and from one side of the CU feed one socket with items that I don’t want interrupted (CCTV network) and the mains side of the generator changeover.
Generator supplies the other side of the changeover.
So normal operation would be mains single phase input fed to L1+L2+L3 on the changeover input
Output from the changeover would be :
L1 – workshop 1 (other side of the split load board)
L2 – workshop 2
L3 to heaters. (roughly balanced across the phases)
When the generator is running it will disconnect from the mains and supply these single phase loads.
Am I mad to even consider such stupidity?
If not is there anything in the regs to forbid this setup?
If there is still any glimmer of hope then any specific areas to pay particular care about?
I realise that this is an overly complex solution to a non existent problem but it has proven to be an interesting thought experiment so far to work around the technical difficulties and come up with a workable solution and if it is all for nothing then it was good fun none the less!
I have all of the components required so there is no cost involved its just one of those brain farts that’s taken on a life of its own
While this is my own property not a customer I obviously want to do it within the regs and my head is spinning and I don’t want to miss anything as selective optimism is easy to indulge when you are looking to make it work.
To set the scene – I have a couple of workshops fed from a domestic single phase supply.
I also have a 50KVA 3-phase generator supplying machinery within the workshops as required.
At present the 2 systems are separate
Up to this point all is well, however, I had the “sensible “ idea that while the generator is running I might as well supply the workshops single phase requirements…………
I have a 3 phase transfer panel and while I know I can achieve the desired outcome it is so unorthodox that I would appreciate a sanity check.
First off the changeover is delayed and has mechanical interlocks so mains and generated supplies remain isolated from each other in all circumstances.
The plan would be to have the single phase supply come in to a split load CU and from one side of the CU feed one socket with items that I don’t want interrupted (CCTV network) and the mains side of the generator changeover.
Generator supplies the other side of the changeover.
So normal operation would be mains single phase input fed to L1+L2+L3 on the changeover input
Output from the changeover would be :
L1 – workshop 1 (other side of the split load board)
L2 – workshop 2
L3 to heaters. (roughly balanced across the phases)
When the generator is running it will disconnect from the mains and supply these single phase loads.
Am I mad to even consider such stupidity?
If not is there anything in the regs to forbid this setup?
If there is still any glimmer of hope then any specific areas to pay particular care about?
I realise that this is an overly complex solution to a non existent problem but it has proven to be an interesting thought experiment so far to work around the technical difficulties and come up with a workable solution and if it is all for nothing then it was good fun none the less!
I have all of the components required so there is no cost involved its just one of those brain farts that’s taken on a life of its own