Meter Maids

Talk Electrician Forum

Help Support Talk Electrician Forum:

This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.
There is more to this storey, it must of been an de energised property.
However they should not have cut the cable.
 
There is more to this storey, it must of been an de energised property.
However they should not have cut the cable.
Or they just furked up. Probably didn't understand how to deal with the cable and buggered off. There's no excuse for leaving a property without a supply. If they couldn't do the job, they should have left it alone.
 
Or they just furked up. Probably didn't understand how to deal with the cable and buggered off. There's no excuse for leaving a property without a supply. If they couldn't do the job, they should have left it alone.
Technically they have a supply 230V on the screws of the isolator. Energised meter. If the supply was de energised that's all the meter op will do is fit meter fit isolator. As for the cut cable I can't answer that, we have to go on what we are told.
 
Technically they have a supply 230V on the screws of the isolator. Energised meter. If the supply was de energised that's all the meter op will do is fit meter fit isolator. As for the cut cable I can't answer that, we have to go on what we are told.
The system is a shambles. If you request a supply (and meter) move, it takes 3 people. The DNO who move the supply head. Then the meter man comes and moves the meter but does NOT connect the output, then the electrician connects the output to the CU.

Seen this pantomime play out several times on new build or refurbishments. Best of luck getting DNO and meter man on the same day.
 
The system is a shambles. If you request a supply (and meter) move, it takes 3 people. The DNO who move the supply head. Then the meter man comes and moves the meter but does NOT connect the output, then the electrician connects the output to the CU.

Seen this pantomime play out several times on new build or refurbishments. Best of luck getting DNO and meter man on the same day.
It's geared up for self connect most new builds like this arrangement.
 