hello chaps,
have to fit a oven rated at 4.9kw, the old one is pluged in so have to run a new circuit in.
the cu is a old wylex with mcb's with no spare ways, cu mounted tight to celing with no chance of taking boards up.
so was thinking of instaling a shower unit with a 32a next to the cu, but with no spare way and unlikely to be able to get the tails out to split, i was wondering if i could use 10mm2 tails (if there is such a thing) and take from the mainswitch with the existing tails.
does this sound ok?
also if you split the tails or use a mcb as a submain feed, how is the best way to cert the job with out exess paper work.
thanks
paul
have to fit a oven rated at 4.9kw, the old one is pluged in so have to run a new circuit in.
the cu is a old wylex with mcb's with no spare ways, cu mounted tight to celing with no chance of taking boards up.
so was thinking of instaling a shower unit with a 32a next to the cu, but with no spare way and unlikely to be able to get the tails out to split, i was wondering if i could use 10mm2 tails (if there is such a thing) and take from the mainswitch with the existing tails.
does this sound ok?
also if you split the tails or use a mcb as a submain feed, how is the best way to cert the job with out exess paper work.
thanks
paul