Ian Speirs
Senior Member
Hi, does anyone use the nic software to fill in pir results.
I was asked to take the laptop on site and fill it in the other day, it was the first time i had used it and was only shown briefley how to build the report up.
I was testing in a very small church with a 3 phase tn-s supply, tails from meter into 4 lucy blocks.
Line 1 lucy block supplying 16 way hagar single phase DB via 25mm tails.
Line 2 lucy block was not supplying anything.
Line 3 Lucy block was supplying an older wylex 4 way 3036 DB via 16mm tails.
No water or gas or metal structure.
When building the report is seemeed that the report would fail to validate as there were 2 DBs connected directly to the source, does this mean that i need to fill out a periodic inspection report, supply characteristics and earthing arrangements, and schedule of inspections for each board connected directly to the origin?
I guess what i'm trying to ask is if the supply tails are split after the meter using lucy blocks, does this require filling out a full pir for each one?
I know i would only use an extra schedule of test results for distribution circuits, but am unsure of how to go about filling in when more than one is connected directly to the origin. Any help would be appreciated. Thanks. :^O
I was asked to take the laptop on site and fill it in the other day, it was the first time i had used it and was only shown briefley how to build the report up.
I was testing in a very small church with a 3 phase tn-s supply, tails from meter into 4 lucy blocks.
Line 1 lucy block supplying 16 way hagar single phase DB via 25mm tails.
Line 2 lucy block was not supplying anything.
Line 3 Lucy block was supplying an older wylex 4 way 3036 DB via 16mm tails.
No water or gas or metal structure.
When building the report is seemeed that the report would fail to validate as there were 2 DBs connected directly to the source, does this mean that i need to fill out a periodic inspection report, supply characteristics and earthing arrangements, and schedule of inspections for each board connected directly to the origin?
I guess what i'm trying to ask is if the supply tails are split after the meter using lucy blocks, does this require filling out a full pir for each one?
I know i would only use an extra schedule of test results for distribution circuits, but am unsure of how to go about filling in when more than one is connected directly to the origin. Any help would be appreciated. Thanks. :^O