Hi there, this is my first post so please go easy on me!! Grin.
I start a new job tomorrow after being unemployed for almost 12 months, I only found out that I had the interview today or I would have found out the answer to my question before now and not left it to the last minute. I so want to make a good impression.
I do have my 2391, but the following has confused me.
I think its quite a simple question if I can explain it properly, so here goes.......
The wires from the solar panels feed a double pole DC isolator in the loft, this isolator feeds the inverter.
The inverter feeds a double pole AC isolator which is also in the loft. This isolator feeds a monitoring unit in the mains cupboard in the house, this moitoring unit feeds a lockable double pole AC isolator, which inturn feeds a new 1-way mains unit which is positioned next to the original house consumer unit.
My questions are as followed....
Do I take my Ze at the inverter or at my new 1-way mains unit?
Do I take my Zs at the inverter or at my new 1 way mains unit?
Do I take my Pefc and Pscc at the inverter or the new 1-way mains unit?
Im guessing it doesn't mater which end I do my R1 + R2 or my Insulation resistance. Spose im confused because the electricity is all going backwards!! Ha! Ha!
Thanks in advance, if you can get me the answers by 7am tomorrow morning then I owe you a night in the pub!!
Blank.
I start a new job tomorrow after being unemployed for almost 12 months, I only found out that I had the interview today or I would have found out the answer to my question before now and not left it to the last minute. I so want to make a good impression.
I do have my 2391, but the following has confused me.
I think its quite a simple question if I can explain it properly, so here goes.......
The wires from the solar panels feed a double pole DC isolator in the loft, this isolator feeds the inverter.
The inverter feeds a double pole AC isolator which is also in the loft. This isolator feeds a monitoring unit in the mains cupboard in the house, this moitoring unit feeds a lockable double pole AC isolator, which inturn feeds a new 1-way mains unit which is positioned next to the original house consumer unit.
My questions are as followed....
Do I take my Ze at the inverter or at my new 1-way mains unit?
Do I take my Zs at the inverter or at my new 1 way mains unit?
Do I take my Pefc and Pscc at the inverter or the new 1-way mains unit?
Im guessing it doesn't mater which end I do my R1 + R2 or my Insulation resistance. Spose im confused because the electricity is all going backwards!! Ha! Ha!
Thanks in advance, if you can get me the answers by 7am tomorrow morning then I owe you a night in the pub!!