sparky b
Well-known member
- Joined
- Jun 21, 2010
- Messages
- 472
- Reaction score
- 0
Just completed a 3 day PV domestic installers course, was alot easier than I thought it was going to be.....
It covered domestic installs, grid connected upto 5kwp...
Some bits that surprised me were:
It back feeds the power through customers cu/db via a spare way (if available)
Install can run on 4mm cable
It's classed as a distribution circuit, so has a 5 second cut off time
There is alot more to it but don't want to make this a long winded post, please ask for more info...
B.
It covered domestic installs, grid connected upto 5kwp...
Some bits that surprised me were:
It back feeds the power through customers cu/db via a spare way (if available)
Install can run on 4mm cable
It's classed as a distribution circuit, so has a 5 second cut off time
There is alot more to it but don't want to make this a long winded post, please ask for more info...
B.