Bonding Services Linking 2 Buildings

Talk Electrician Forum

Help Support Talk Electrician Forum:

This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.
Still trying to decide what to do! 

Bond both services in both buildings with 50mm. 

or, 

Bond main building with 50mm and the new unit with 10mm.

Decisions.

Cheers

GS

 
Still trying to decide what to do! 

Bond both services in both buildings with 50mm. 

or, 

Bond main building with 50mm and the new unit with 10mm.

Decisions.

Cheers

GS
If you are going to get a fault current along the services between the two buildings, then that fault current will be the same at both ends. So surely same size bonding at both ends?

 
If you are going to get a fault current along the services between the two buildings, then that fault current will be the same at both ends. So surely same size bonding at both ends?
50mm bond in both buildings. 

Iv'e CMA then. 

Cheers lads. 

GS

 