Well, just a quick post, not put much thought into it at the moment, just a feeler for ideas.
I have a bit of an issue.
It seems I need to run a gas bond in, none present, into a listed church, not sure which grade, but that is not quite critical, yet.
It is around a 55m run with the only feasible route 4m above ffl.
The route is around the perimeter at wall plate level.
Church is in regular use, pews in the way, and the roof design is not really helpful for ladder use.
Around the outside is even longer, and, would look rubbish, plus we'd have to run it by CADW.
I'm open to suggestions.
TN-S though probably TN-C-S outside the walls!
That is not quite relevant though.
DNO transformer about 5m from the corner of the church in the grounds!
Lots of beams in the way, flooring at different levels near the walls.
One span of around 8m has no wall plate, so would need to go from wall plate level 4m, to pitch roof level and follow this and add probably 20m to the run, and require access at around 10m!
Suggestions please?
I have a bit of an issue.
It seems I need to run a gas bond in, none present, into a listed church, not sure which grade, but that is not quite critical, yet.
It is around a 55m run with the only feasible route 4m above ffl.
The route is around the perimeter at wall plate level.
Church is in regular use, pews in the way, and the roof design is not really helpful for ladder use.
Around the outside is even longer, and, would look rubbish, plus we'd have to run it by CADW.
I'm open to suggestions.
TN-S though probably TN-C-S outside the walls!
That is not quite relevant though.
DNO transformer about 5m from the corner of the church in the grounds!
Lots of beams in the way, flooring at different levels near the walls.
One span of around 8m has no wall plate, so would need to go from wall plate level 4m, to pitch roof level and follow this and add probably 20m to the run, and require access at around 10m!
Suggestions please?