Its ALWAYS the electrics that have to be moved .
Years back I was wiring a new build health centre , single storey , basically twin /earth through ceiling joists , all our wiring was in when the security firm roll up , named after a freshwater fish .
I went to another job for two days , returned to find the guy still there and his alarm wiring passing through my joist holes with the lighting & power .
Told the guy he shouldn't have done that , running 12V stuff with 240V , he said our cable was rated at 600V so it was all fine .
Because the place was being build by the City council their Clerk of Works (Electrical) turns up & tries to haul me over the coals for mixing voltages & phoned my boss telling him to get extra labour out there to drill new holes , pull all the wiring out & do it properly .
Years back I was wiring a new build health centre , single storey , basically twin /earth through ceiling joists , all our wiring was in when the security firm roll up , named after a freshwater fish .
I went to another job for two days , returned to find the guy still there and his alarm wiring passing through my joist holes with the lighting & power .
Told the guy he shouldn't have done that , running 12V stuff with 240V , he said our cable was rated at 600V so it was all fine .
Because the place was being build by the City council their Clerk of Works (Electrical) turns up & tries to haul me over the coals for mixing voltages & phoned my boss telling him to get extra labour out there to drill new holes , pull all the wiring out & do it properly .