Hi everyone please can someone help!
I have had an extesion built with underfloor heating (UFH) installed. As my gravity fed system wasn't up to the task I had a Combi system installed. In his wisdom the plumber removed the Hot water tank, and helpfully replaced it with a flow and return ready for the UFH isolated by the old three port mid position valve. I assume this would be classed as a Y plan allowing for UFH only, CH only or both!!!
The problems came when wireing the controls from the UFH and CH separatly to the 3 port valve. On the first attempt we had hot water going to the CH at the same time as the UFH even when the CH was set to off. (this is because i think the vale was in mid position)
On the second attempt the CH stays hot when UFH is on and calling by doesnt get any hot water so stays on (house boiling, extension cold!!!! (this is because the valve has motored to CH only but not returned when satisfied.
The builder has had a new controller fitted to the wocester bosh boiler for the extra tap!! and replaced the room stat for a stat/programmer.... but still failed to set it up right. Now he wants to blaim the plumber....
Question - is it possible to have this system working with the current Y plan valve or would we need to switch to an S plan system for simplicity? ( I assume this will need to re plumbed)
There are currently five cables entering the control box which I assume are 1x boiler control, 1x programmer, 1x room state. 1x UFH stat and another from the UFH possibly programmer??
There is of cause the 3 port valve cable.
I would post pic but im new to forum and dont know how??
Any help would be appreciated as im fed up of being taken for a ride having payed a lot of money for a lemon so far....
Dave
I have had an extesion built with underfloor heating (UFH) installed. As my gravity fed system wasn't up to the task I had a Combi system installed. In his wisdom the plumber removed the Hot water tank, and helpfully replaced it with a flow and return ready for the UFH isolated by the old three port mid position valve. I assume this would be classed as a Y plan allowing for UFH only, CH only or both!!!
The problems came when wireing the controls from the UFH and CH separatly to the 3 port valve. On the first attempt we had hot water going to the CH at the same time as the UFH even when the CH was set to off. (this is because i think the vale was in mid position)
On the second attempt the CH stays hot when UFH is on and calling by doesnt get any hot water so stays on (house boiling, extension cold!!!! (this is because the valve has motored to CH only but not returned when satisfied.
The builder has had a new controller fitted to the wocester bosh boiler for the extra tap!! and replaced the room stat for a stat/programmer.... but still failed to set it up right. Now he wants to blaim the plumber....
Question - is it possible to have this system working with the current Y plan valve or would we need to switch to an S plan system for simplicity? ( I assume this will need to re plumbed)
There are currently five cables entering the control box which I assume are 1x boiler control, 1x programmer, 1x room state. 1x UFH stat and another from the UFH possibly programmer??
There is of cause the 3 port valve cable.
I would post pic but im new to forum and dont know how??
Any help would be appreciated as im fed up of being taken for a ride having payed a lot of money for a lemon so far....
Dave