OK so for instance I could use a 10 way split con household circuits on 1 side on other side replace the RCD with a main switch and feed the E7 tails into that feeding the fuses that sound right?If you are going with all RCBOs then just use an Enclosure big enough for ALL the circuits, install 2 Main switches and fit two Busbars.Most boads already have split load option N bar, so really you just make up you own Unit.
Did one recently using Metal Clad Enclosure as the existing suppy to the Flat was a 4 Core SWA 2 cores 24 Hour supply and 2 Cores Off peak.
Used Control gear BASIC range from Denmans