completing Form 4 - Schedule of test results

Talk Electrician Forum

Help Support Talk Electrician Forum:

This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.
Forgot to ask tho...do you number the spareways for clarification on the test sheet and just dash through the results boxes, or omit them?

Many thanks.
I must admit i never used to record the spare ways until the NICEIC inspector told me i must:O so now i do. ;)

 
yep

eg

main switch

1 outside socket ,,,,

2 spare

RCD1

3 shower ,,,,,,,,

4 sockets kitchen ,,,,,,,,

RCD 2

5 cooker ,,,,,,,

6 sockets house

7 lights upstairs ,,,,,,,,

8 spare

RCD 3

9 lights downstairs ,,,,,,

10 spare

11 attic socket

12 spare

obviously only an example, tho I do still tend to put higher rated MCBs to the right hand side of each group when possible, merely cos i was always taught that way and I see at as good practice.

 