Call today, from the same guys I wrote about yesterday:
They`ve got a commecial property, with 2 x 4KW installs. 32 NSI panels, and Diehl Ako 3800S x 2.
Now, because most of last year we had NSI 96-M panels, which have a Voc of 59.8, we were having 2 strings of 8.
So these pratts have 4 strings coming from the roof..........only these panels aren`t 96-M`s, and only have a Voc of 35V :Chair fall
The scaff has been removed, and its a 4 storey building.
The reason for the `phone call? " We don`t know why they don`t work".
So I told `em.
"Can we do anything from the ground, or do I have to pay for scaff to go back up?"
" It can be done from the ground, but it is against H&S, MCS, 7671 and your PLI rules. Furthermore, if your "spark" can`t work out how to do it, he isn`t competent to attempt it - so I`m not going to explain it to him."
.........Is it just me?
Or are these people thicker `n a brick?
p.s. They`ve just been on, sat and (presumably) passed a PV course. :innocent
ROTFWL :slap
They`ve got a commecial property, with 2 x 4KW installs. 32 NSI panels, and Diehl Ako 3800S x 2.
Now, because most of last year we had NSI 96-M panels, which have a Voc of 59.8, we were having 2 strings of 8.
So these pratts have 4 strings coming from the roof..........only these panels aren`t 96-M`s, and only have a Voc of 35V :Chair fall
The scaff has been removed, and its a 4 storey building.
The reason for the `phone call? " We don`t know why they don`t work".
So I told `em.
"Can we do anything from the ground, or do I have to pay for scaff to go back up?"
" It can be done from the ground, but it is against H&S, MCS, 7671 and your PLI rules. Furthermore, if your "spark" can`t work out how to do it, he isn`t competent to attempt it - so I`m not going to explain it to him."
.........Is it just me?
Or are these people thicker `n a brick?
p.s. They`ve just been on, sat and (presumably) passed a PV course. :innocent