Hi guys, I am a qualified PV installer and registered with NAPIT as defined scope so am able to connect pv into cu and do all relevant tests.But I have a job coming up with no spare way in the cu so I have to fit an additional cu (probably 2-way rcd protected).Am I right in saying that I have to fit a henlly block between the meter and existing cu then run seperate tails to the existing and new cu's (in parallel).
1)Should the tails be 25mm or 16mm?
2)Do I take the earth for the new cu from the main earth terminal (not the existing cu)and does it have to be 16mm or 10mm?
3)I assume I only do all the relevent tests on the new circuit and supply Ze.
4)Finally, I have been told that the DNO may charge upto
1)Should the tails be 25mm or 16mm?
2)Do I take the earth for the new cu from the main earth terminal (not the existing cu)and does it have to be 16mm or 10mm?
3)I assume I only do all the relevent tests on the new circuit and supply Ze.
4)Finally, I have been told that the DNO may charge upto