whether doing minor or major work, i know the bonding should be checked and if it is non existent it should be installed before any work commences, what if the installation has bonding of 6mm and there is no sign of deteriation, continuity checks out o.k. and the work is fairly minor, say installation of a new circuit. would it be required to upgrade the bonding? If the work was major i would upgrade the bonding anyway. i would be inclined to leave 6mm for tt, have read the regs and not clear about tn-c-s or tn-s. Any help appreciated.