hey lads its been a long time, since i was an apprentice, since i did 3phase so can someone help me out with cable size and 3p mcb required
all i know is the machine is a bench saw rated at max 45A total not per phase
cable length is going to be @25m
if memory serves ive calculated max demand will be @27kw
and with p.f of 0.9 gives a rating of 13.5A per phase
does this sound right?
as the run in to be in box trunking i was going to use sy 5 core because of the drop from the box trunking down to the isolator
have i missed anything or am i right? wrong? close? lol...
thanks in advance lads
all i know is the machine is a bench saw rated at max 45A total not per phase
cable length is going to be @25m
if memory serves ive calculated max demand will be @27kw
and with p.f of 0.9 gives a rating of 13.5A per phase
does this sound right?
as the run in to be in box trunking i was going to use sy 5 core because of the drop from the box trunking down to the isolator
have i missed anything or am i right? wrong? close? lol...
thanks in advance lads