Quick question
how long will this take to do ???
double garage to be partioned to provide new office
15m swa buried for 5m coming from meter
new cu
6 double sockets
2 pendants
outside light
outside socket
smoke alarm
old part of garage
2 doubles 4 pendants 2 of switch in loft space
testing
because im working in conjunction with the builders so maybe a bit of backwards/forwards travelling (30miles each way) im thinking 3 or 4 days
but dont know which to price on
cheers
how long will this take to do ???
double garage to be partioned to provide new office
15m swa buried for 5m coming from meter
new cu
6 double sockets
2 pendants
outside light
outside socket
smoke alarm
old part of garage
2 doubles 4 pendants 2 of switch in loft space
testing
because im working in conjunction with the builders so maybe a bit of backwards/forwards travelling (30miles each way) im thinking 3 or 4 days
but dont know which to price on
cheers