Hi all i have read the other threads on this subject but am going to post this anyway just to get things clear in my head...well tryto anyway lol.
im going to be moving a C.U from one side of a room to the other. About 6m. it is in a small terraced house,two up two down, am i right in thinking that as long as i install a Fused Isolator. (was going to use the 60A wylex type as this will give me some discrimination before the 80A EDF fuse)
Then i should be able to install the 25mm tails up to this length? they are going to be installed outside the house in a trunking then through the wall and into the new C.U position.
I have looked up in the O.S.G page 17 and looked at the regs it reffers to but can not find any deffinate answers. If you know what REG i should be looking at then i would like to know that aswell please for future refferance and all that
thanks for taking the time to read this lot
John
im going to be moving a C.U from one side of a room to the other. About 6m. it is in a small terraced house,two up two down, am i right in thinking that as long as i install a Fused Isolator. (was going to use the 60A wylex type as this will give me some discrimination before the 80A EDF fuse)
Then i should be able to install the 25mm tails up to this length? they are going to be installed outside the house in a trunking then through the wall and into the new C.U position.
I have looked up in the O.S.G page 17 and looked at the regs it reffers to but can not find any deffinate answers. If you know what REG i should be looking at then i would like to know that aswell please for future refferance and all that
thanks for taking the time to read this lot
John