My second application this year, thanks all for helping with previous question with regards to a new connection app.
Current customer has a hotel on single phase, looking at installing 3phase, on the form from electricity northwest section 4 asks the type of supply required.
Options are ()new connection () additional load () service alteration to existing position and 5 others that im sure arent the right ones.
Would i be correct ticking () service alteration to existing position or would it be classed as ()additional load ?