Hey all,
Got a few questions about a portacabin that's going to be used as an office block. Unfortunately I have not seen the cabin and doubt I will until it turns up unannounced no doubt. The cabin is 75m away from the closest supply which will be run underground in ducts (already in place). I am planning on supplying a 63A single phase supply using 25mmsq 3C swa (due to length of the run). The supply is TNS so no need to earth rod. Do I need to make any other considerations? Input greatly recieved.
S
Got a few questions about a portacabin that's going to be used as an office block. Unfortunately I have not seen the cabin and doubt I will until it turns up unannounced no doubt. The cabin is 75m away from the closest supply which will be run underground in ducts (already in place). I am planning on supplying a 63A single phase supply using 25mmsq 3C swa (due to length of the run). The supply is TNS so no need to earth rod. Do I need to make any other considerations? Input greatly recieved.