Various sparks who came to work for us had their own ideas on how to interpret the Regs . This was five of them that stuck with me . ( Yes I know I 've done them before )
1. Steel conduit . Only one runner is allowed per installation . This was viewed by one guy as , say , the whole of this factory , all done in steel conduit , if you use a runner on day one
thats it ! Can't have another on the site !!!! ( In fact what was frowned upon was if you made up a conduit run and fitted it in using a runner at both ends ) Could never see the problem myself TBH
2. On house bashing you can't fit a pendant in a kitchen . :C
3. You cannot pass a neutral through a switch ( See sketch ) :C
4. You cannot pass ring main cables through socket boxes ( See sketch ) :C
5. You cannot run stuff horizontally anyway :C
1. Steel conduit . Only one runner is allowed per installation . This was viewed by one guy as , say , the whole of this factory , all done in steel conduit , if you use a runner on day one
thats it ! Can't have another on the site !!!! ( In fact what was frowned upon was if you made up a conduit run and fitted it in using a runner at both ends ) Could never see the problem myself TBH
2. On house bashing you can't fit a pendant in a kitchen . :C
3. You cannot pass a neutral through a switch ( See sketch ) :C
4. You cannot pass ring main cables through socket boxes ( See sketch ) :C
5. You cannot run stuff horizontally anyway :C