1. The feed is supplying the spraying & baking booth direct - do seperate DB.
2. They REALLY want to keep cost down. Ergo the 3 core DNO cable.
3. The FS at the booth is only 20A/phase. Can`t allow much over that anyway, as the garage DB is heaving as it is. Probably have to sub it just to make space for the breaker.
On that point, I`ll have to take a photo of the DB when I`m there. They`ve been DIY adding to the install. No cover on DB (at all!!), cables coming from all over the place.
Am I looking forward to that bit of nonsense...........NOT:_|